BHEL commissions 363 MW power project in Tripura
November 17, 2014 9:02 pm
November 17, 2014 9:02 pm
Bharat Heavy Electricals Ltd. (BHEL) has announced the commissioning the second module of the two 363.3 MW gas-based Combined Cycle Power Plant (CCPP) of ONGC Thermal Power Corporation (OTPC) in Tripura.
Located at Palatana in Udaipur district of Tripura, around 50 kms from Agartala, the CCPP comprises two modules of 363.3 MW each equipped with fuel efficient advanced class Frame 9FA gas turbines. BHEL had won the contract for setting up the CCPP on EPC (Engineering, Procurement & Construction) basis, against International Competitive Bidding (ICB).
With the commissioning of this module, BHEL has commissioned nine modules of Frame 9FA gas turbines in the combined cycle mode, in India.
BHEL has so far commissioned 911 MW of gas-based and hydro sets in Tripura which accounts for 100 per cent of the states generating capacity. BHEL had earlier commissioned 14 gas turbines of smaller rating upto 21 MW in Tripura as the sizes were limited by logistic constraint. The Palatana project is the first and the largest of its kind in the entire North-Eastern part of India. BHEL is also executing a gas-based project of 100 MW of NEEPCO at Monarchak in Tripura.
We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.
November 17, 2014 2:02 pm
Bharat Heavy Electricals Ltd. (BHEL) has announced the commissioning the second module of the two 363.3 MW gas-based Combined Cycle Power Plant (CCPP) of ONGC Thermal Power Corporation (OTPC) in Tripura.
Located at Palatana in Udaipur district of Tripura, around 50 kms from Agartala, the CCPP comprises two modules of 363.3 MW each equipped with fuel efficient advanced class Frame 9FA gas turbines. BHEL had won the contract for setting up the CCPP on EPC (Engineering, Procurement & Construction) basis, against International Competitive Bidding (ICB).
With the commissioning of this module, BHEL has commissioned nine modules of Frame 9FA gas turbines in the combined cycle mode, in India.
BHEL has so far commissioned 911 MW of gas-based and hydro sets in Tripura which accounts for 100 per cent of the states generating capacity. BHEL had earlier commissioned 14 gas turbines of smaller rating upto 21 MW in Tripura as the sizes were limited by logistic constraint. The Palatana project is the first and the largest of its kind in the entire North-Eastern part of India. BHEL is also executing a gas-based project of 100 MW of NEEPCO at Monarchak in Tripura.