600 MW Hydro Power Plant of NEEPCO synchronises its last unit

By January 20, 2021 3:36 pm IST

600 MW Hydro Power Plant of NEEPCO synchronises its last unit
.

150 mw unit 4 of lament hydroelectric project synchronised with the grid. With this accomplishment the goal of 600mw Kameng hydroelectric power is achieved.

NEEPCO has successfully synchronized the fourth generating unit of 150 MW (unit-4) of its giant 600 MW Kameng Hydro Power Plant with the grid on 19th Jan 2021. Units-1, 2, and 3 of 150 MW each have already been commissioned earlier in June, July 2020 and Jan 2021 respectively.

Advertising

EPR Android App Banner

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Tags: News
Nirmal Wires
Nirmal Wires
Android App
Android App

Events

Wiretech 2025
Wiretech 2025
Power Gen
Power Gen
World Utilities Congress
World Utilities Congress
India Green Energy Expo
India Green Energy Expo

Our Sponsors

Rayzon Solar Pvt Ltd
Rayzon Solar Pvt Ltd
Om Technical Solutions
Om Technical Solutions
Harting
Harting
Doble Engineering
Doble Engineering
CSE Power
CSE Power
Nirmal
Nirmal
Ravin Group
Ravin Group
Meco Instruments Pvt Ltd
Meco Instruments Pvt Ltd
Neo Tele Tronixl Pvt Ltd
Neo Tele Tronixl Pvt Ltd
ZIEHL ABEGG
ZIEHL ABEGG
Power Electronical
Power Electronical
Deep Sea Electronics
Deep Sea Electronics
Supremesolar
Supremesolar
Elev8 Lift
Elev8 Lift
Synthesis Winding Technologies Pvt Ltd
Synthesis Winding Technologies Pvt Ltd
flir system
flir system
Electrotherment
Electrotherment
Aeron Composite Pvt Ltd
Aeron Composite Pvt Ltd
Powerica LTD
Powerica LTD
Eaton
Eaton
AEEPL
AEEPL
MENNEKES Electric India
MENNEKES Electric India
PRAMA HIKVISION INDIA
PRAMA HIKVISION INDIA