EPR Subscription Banner
EPR Subscription Banner
Promonique Banner
Promonique Banner
Home » Special Report » Right of Way (ROW) Challenges in the Construction of Transmission lines

Right of Way (ROW) Challenges in the Construction of Transmission lines

By EPR Magazine Editorial November 30, 2022 3:58 pm

Right of Way (ROW) Challenges in the  Construction of Transmission lines
.

At the COP26 summit in Glasgow in Nov’2021, India pledged 500 GW of non-fossil fuel-based installed capacity by 2030 and agreed to meet 50 per cent of its energy requirement by renewable sources. To meet this ambitious target, many solar parks, hybrid wind-solar power projects, and offshore wind plants are under development.
Also, various new technologies are being introduced in grid-like Battery Energy Storage Systems (BESS) and Green Hydrogen Energy to reduce the carbon footprint. Globally, work is going on for developing the One Sun, One World, One Grid (OSOWOG). A matching transmission infrastructure shall be required to evacuate this massive quantum of renewable power. Moreover, with the gestation period of renewable power projects being less, building transmission infrastructure in a shorter time is a big challenge being faced by planners.
India is developing green energy corridors to evacuate renewable energy from generation points to the load centres by creating intra-state and inter-state transmission infrastructure through Regulatory Tariff Mechanism (RTM) and Tariff Based Competitive Bidding (TBCB) routes. Land acquisition and getting right of way (ROW) are becoming the biggest hurdles in constructing the transmission infrastructure in time due to rapid urbanisation and litigation issues. This paper aims to give information about the ROW and how it is a significant challenge for transmission utilities/ companies in Construction, O and M phases and the mitigation measures.
Introduction
Power transmission and other infrastructure projects generally face various issues relating to environmental/ forest clearances/ approvals, land acquisitions, ROW, and local resistance during their construction. India’s electricity demand is increasing rapidly due to industrial development, increased rural electrification and urbanisation. Accordingly, transmission and distribution networks are required to meet the increasing electricity demand. With the strong emphasis on renewable energy sources, mostly located in remote areas, their integration into the grid requires massive transmission infrastructure and that, too, in a shorter time frame. The construction of transmission lines is becoming more challenging every day because of getting the right of way, acquiring land and various statutory and environmental clearances. Due to increasing awareness and rapid urbanisation, it is getting tough to get right of way and route through urban areas, public parks, near schools, playgrounds, forest areas, wildlife corridors and in urban slums, metropolitan areas, public parks, etc., pose a severe challenge.
Govt of India, vide circular dated Oct 15, 2015, developed the guidelines for ROW compensation payment for resolving the ROW and early completion of transmission projects, including the tower base land and corridor land value compensation.
The various laws/acts relating to ROW compensation, litigation and land acquisition are The Telegraph Act of 1885, The Electricity Act of 2003, The Land Acquisition Act of 1894, The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Amendment) Ordinance, 2014, The Forest (Conservation) Act, 1980, The Wildlife (Protection) Act, 1972, The Environmental (Protection) Act, 1986, The Indian Electricity (IE) Rules (77, 80(1), 80(2) for clearance), The Indian Limitation Act, 1963, The Work of Licensees Rule, 2006 Indian Standard IS-5613 etc.

Right of Way Corridor – Statutory Provisions

The right of way in a transmission line is a strip of land required by a utility for constructing, maintaining and protecting its transmission line. Right of Way, also named as transmission corridor, is the minimum safety corridor around power lines to meet the required safety clearances and the electromagnetic field exposure limits. It allows the utility to keep the power lines clear of tall trees, buildings and other obstacles that may interfere with line operation and to ensure the safety of the public and environment.
The essential laws governing the right of way are the Indian Telegraph Act of 1885 and the Electricity Act of 2003. The provision contained in Sections 12 to 18 of the Electricity Act of 1910 remained in force until the rules under Sections 67 to 69 of the Electricity Act of 2003 were made. Also, the procedure and provisions under Sections 12 to 18 of the Electricity Act 1910 needed to be more adequate for major Generation or Transmission Projects. Hence, the express provision for speedy execution is made under Section 164 of the Electricity Act, 2003. (Previously under Section 42 of the Electricity Supply Act, 1948).
Section 67 of the Electricity Act, 2003 provides for a licensee to lay down interalia, electric supply lines, electric plant and other works and to do all other acts necessary for transmission or supply of electricity. It also stipulates that a licensee shall cause minor damage and fully compensate for any damage caused. In case of any difference or dispute, the matter shall be determined by the appropriate commission.
Section 68 of the Electricity Act 2003 has provisions relating to overhead lines. It interalia stipulates that where any tree or any structure or other object interrupts or interferes with, or is likely to interrupt or interfere with, the transmission of electricity or the accessibility of any works, an executive magistrate or authority specified by the appropriate government may, on the application of the licensee, cause the tree, structure or object to be removed or award compensation considering its existence before or after the placing of the overhead line.
Section 69 of the Electricity Act 2003 has a provision related to giving notice to the Telegraph Authority.
Section 164 of the Electricity Act, 2003 empowers the Appropriate Government to confer upon any public officer, licensee, or any other person engaged in the business of supplying electricity any of the powers which the telegraph authority possesses under the Indian Telegraph Act, 1885 (13 of 1885) concerning the placing of telegraph lines.
The critical sections of the Telegraph Act are Section 10 and Section 16. Section 10 of the Telegraph Act 1885 empowers the transmission company to place towers in or upon the immovable property. However, while doing so, the company shall not acquire any right other than that of a user in the property. The company shall do as minor damage as possible and, after completion of work, shall pay total compensation to all persons interested for any damage they sustained because of the exercise of those powers.
Section 16 of the Telegraph Act 1885 assigns the District Magistrate power to clear the obstruction. If the obstruction continues even after making an order by the District Magistrate under sec.16 (1), the obstructor shall have committed an offence under Sec.188 (45 of 1860) of the Indian Panel Code.
The electricity company must decide and pay the compensation. While determining the reasonable and realistic amount of compensation, the company may get it done from or with the help of the following respective authorities:

  • Revenue Authorities: – For Crops, non-schedule Trees
  • Forest Authorities: – For Schedule Trees like Teak.
  • Horticulture Dept.:- Fruit Bearing Trees.
  • Agriculture Dept: – Value of Crop damage.
  • Rubber Board: – Rubber trees.

Disputes regarding the sufficiency of compensation shall be decided by the District Judge after receiving an application from any party concerned.
For the filling of Trees, the utility will have to take permission from a Tree officer under the Felling of Tree regulation act and the Preservation of Tree Act. Forest approval is required for laying the transmission lines through Forest.
Authored by Rajesh Gupta, Director, NETCL and Harshal Malewar, Deputy Manager, NETCL(JV of POWERGRID and OTPC)

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Android App
Android App
EPR EMagazine October 2024
EPR EMagazine October 2024
EPR EMagazine October 2024

Events

REI Expo
REI Expo
Green Hydrogen Summit
Green Hydrogen Summit
Enlit Asia
Enlit Asia
Windergy
Windergy
PTC Asia
PTC Asia
Distribution Utility Meet
Distribution Utility Meet
Auto EV India
Auto EV India
Global Sustainability Expo & Conference
Global Sustainability Expo & Conference
Elecxpo
Elecxpo
India Smart Utility Week
India Smart Utility Week

Our Sponsors

Panasonic Life Solutions India Pvt Ltd
Panasonic Life Solutions India Pvt Ltd
Rayzon Solar Pvt Ltd
Rayzon Solar Pvt Ltd
NBC Bearings
NBC Bearings
Lawson Fuses
Lawson Fuses
Nirmal
Nirmal
Meco Instruments Pvt Ltd
Meco Instruments Pvt Ltd
Waa Cables
Waa Cables
Bask Energies
Bask Energies
Gloster Cables Limited
Gloster Cables Limited
Fevino
Fevino
Elev8 Lift
Elev8 Lift
flir system
flir system
Omicron
Omicron
Sudhir Power
Sudhir Power
CAT
CAT
Electrical Research Development Association
Electrical Research Development Association
Schneider Electric
Schneider Electric
Innovatek
Innovatek
Kirloskar Pumps
Kirloskar Pumps
Electrotherment
Electrotherment
Aeron Composite Pvt Ltd
Aeron Composite Pvt Ltd
Delta
Delta
Goldisolar
Goldisolar
Aamokshsolar
Aamokshsolar
Om Technical Solutions
Om Technical Solutions
Perkins
Perkins
Apil
Apil
Build Smart
Build Smart
KYB Conmat
KYB Conmat
MENNEKES Electric India
MENNEKES Electric India
PRAMA HIKVISION INDIA
PRAMA HIKVISION INDIA