Megger
Megger
Rayzon
Rayzon
EPR Subscription Banner
EPR Subscription Banner
Home » Exclusive » Saving India’s transmission network lines

Saving India’s transmission network lines

By December 11, 2018 11:44 am IST

Saving India’s transmission network lines
.

Transmission lines links the node centres of the country’s generation sector to the end user. The failure of any line would have much worse of an effect. So, here is a special report on how imperative it is to implement an emergency restoration system to save the day.

Emergency Restoration plan in terms of transmission tower will include the complete project planning from the day of enquiry until the line is charged. The first point of action will be to make a site visit by the survey team of Supreme to examine the site condition. Clearance between the existing tower & ERS, span length, possibility of ROW issues needs to be considered while making the survey. This will be followed by dispatching the materials and labours to the site and begin the erection works.

If ERS is used for re-conductoring works, a shutdown will be required for bypassing the main line to the ERS. Once the ERS line is charged, they will be under constant monitoring. After restoring the main line, the bypassed line will be shifted to the main line and the ERS towers will be disassembled.

Limiting the cost and duration of power outages in transmission lines
It takes months to restore a damaged tower back to its original state. Without using
ERS towers, the transmission line utilities will incur a severe financial loss due to the non-availability of their lines.

Advertising

EPR Android App Banner

Successful restorations
During the erection time of our first project, our team took a day for erecting a single tower. We made changes to the erection process and by the time we started doing our third project, we were fully capable of erecting a 36m tower in a matter of hours without the need of any heavy equipments. The major takeaway lesson was from the last project that we did in Eastern India where we erected a tower in middle of a river where there is no proper soil for anchoring the tower. As the accessibility to the site was only by country boats, we designed and made portable bases which acted as a deadweight for anchoring. Prior to this, the most crucial limit on using the ERS structures is that there should be a proper soil for anchoring the structures. With the advent of these modular base, we have taken out one of the major constraints on erecting the ERS towers (i.e) a proper soil for anchoring and there is now no such terrain limit for ERS.

 

Authored by,
Harish Agarwal, CEO, Supreme & Co Pvt ltd

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Nirmal Wires
Nirmal Wires
Android App
Android App

Events

Wiretech 2025
Wiretech 2025
Power Gen
Power Gen
GOTS 2025
GOTS 2025
India Green Energy Expo
India Green Energy Expo

Our Sponsors

Greenfinity Powertech Pvt Ltd
Greenfinity Powertech Pvt Ltd
Rayzon Solar Pvt Ltd
Rayzon Solar Pvt Ltd
Kp Group
Kp Group
Adani Solar
Adani Solar
Fluke
Fluke
Meco Instruments Pvt Ltd
Meco Instruments Pvt Ltd
Icon Solar-En Power
Icon Solar-En Power
Mtekpro Technologies
Mtekpro Technologies
Novasys
Novasys
Testo India
Testo India
Timken
Timken
OEN
OEN
Sun Bond
Sun Bond
Orange Power
Orange Power
S K Industrial
S K Industrial
Elev8 Lift
Elev8 Lift
flir system
flir system
Omicron
Omicron
DEIF
DEIF
Electrotherment
Electrotherment
Aeron Composite Pvt Ltd
Aeron Composite Pvt Ltd
PRAMA HIKVISION INDIA
PRAMA HIKVISION INDIA
Sun Cables
Sun Cables