Promonique
Promonique
Home » Exclusive » Saving India’s transmission network lines

Saving India’s transmission network lines

December 11, 2018 11:44 am

Saving India’s transmission network lines
.

Transmission lines links the node centres of the country’s generation sector to the end user. The failure of any line would have much worse of an effect. So, here is a special report on how imperative it is to implement an emergency restoration system to save the day.

Emergency Restoration plan in terms of transmission tower will include the complete project planning from the day of enquiry until the line is charged. The first point of action will be to make a site visit by the survey team of Supreme to examine the site condition. Clearance between the existing tower & ERS, span length, possibility of ROW issues needs to be considered while making the survey. This will be followed by dispatching the materials and labours to the site and begin the erection works.

If ERS is used for re-conductoring works, a shutdown will be required for bypassing the main line to the ERS. Once the ERS line is charged, they will be under constant monitoring. After restoring the main line, the bypassed line will be shifted to the main line and the ERS towers will be disassembled.

Limiting the cost and duration of power outages in transmission lines
It takes months to restore a damaged tower back to its original state. Without using
ERS towers, the transmission line utilities will incur a severe financial loss due to the non-availability of their lines.

Few years back, in case of major tower failure, large utilities in India imported and trained their team for erecting these structures. Further, small utilities and transmission companies were unable to offer such high capex for importing and maintaining a team for these ERS towers. In order to make it available for the Indian utilities, we designed, tested and manufactured the ERS tower. We have 50-member team available with us who are trained and can make the erection of ERS tower. They are fully capable of erecting a 36m tower within a couple of hours. We offer a complete end to end solution where we handle the transportation, erection, supervision and disassembling of the structure. This has not only cut the capital cost for importing the tower but also saves the O&M, training and storage cost that are incurred by the customer in case they own the system.

Successful restorations
During the erection time of our first project, our team took a day for erecting a single tower. We made changes to the erection process and by the time we started doing our third project, we were fully capable of erecting a 36m tower in a matter of hours without the need of any heavy equipments. The major takeaway lesson was from the last project that we did in Eastern India where we erected a tower in middle of a river where there is no proper soil for anchoring the tower. As the accessibility to the site was only by country boats, we designed and made portable bases which acted as a deadweight for anchoring. Prior to this, the most crucial limit on using the ERS structures is that there should be a proper soil for anchoring the structures. With the advent of these modular base, we have taken out one of the major constraints on erecting the ERS towers (i.e) a proper soil for anchoring and there is now no such terrain limit for ERS.

 

Authored by,
Harish Agarwal, CEO, Supreme & Co Pvt ltd

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Android App
Android App
EPR eMagazine April 2024
EPR eMagazine April 2024
EPR eMagazine April 2024

Events

RenewX India
RenewX India
International Geotechnical Innovation Conference
International Geotechnical Innovation Conference
EL Asia
EL Asia
Global Energy Digitalisation Conclave
Global Energy Digitalisation Conclave
World battery and energy storage industry expo
World battery and energy storage industry expo
Green Hydrogen Summit
Green Hydrogen Summit
POWERGEN India
POWERGEN India
Windergy
Windergy

Our Sponsors

Rayzon Solar Pvt Ltd
Rayzon Solar Pvt Ltd
Doble Engineering
Doble Engineering
Allied Power Solutions
Allied Power Solutions
Nirmal
Nirmal
KEI Industries Limited
KEI Industries Limited
Maco Corporation India Pvt Ltd
Maco Corporation India Pvt Ltd
Meco Instruments Pvt Ltd
Meco Instruments Pvt Ltd
Icon Solar-En Power
Icon Solar-En Power
Novasys
Novasys
Testo India
Testo India
Mecc-Alte India
Mecc-Alte India
Newtech Switchgear
Newtech Switchgear
Triveni Turbine ltd
Triveni Turbine ltd
Aeron Composite Pvt Ltd
Aeron Composite Pvt Ltd
Winsun
Winsun
A-1 ELECTRICALS
A-1 ELECTRICALS
Allied Moulded Enclosure Products
Allied Moulded Enclosure Products
ANUSHREE ELECTRICAL ENGINEERS
ANUSHREE ELECTRICAL ENGINEERS
Ashone Technologies
Ashone Technologies
Citroen Switchgears Pvt. Ltd.
Citroen Switchgears Pvt. Ltd.
Electrotherm
Electrotherm
KVTEK Power Systems
KVTEK Power Systems
MENNEKES Electric India
MENNEKES Electric India
Om Technical Solutions
Om Technical Solutions
PRAMA HIKVISION INDIA
PRAMA HIKVISION INDIA
Motwane Manufacturing
Motwane Manufacturing