NTPC’s subansiri lower hydroelectric project nears completion

By July 4, 2023 4:47 pm IST

NTPC’s subansiri lower hydroelectric project nears completion
.

The milestone was achieved with dam construction at elevation level 210 m above sea level.

The construction of the dam until the top level of Elevation Level (EL) 210 M in all blocks was completed on recently, marking a significant milestone towards completion of the 2,000 Mega Watt Subansiri Lower Hydroelectric Project located in Arunachal Pradesh and Assam and being executed by NHPC Limited. Here, elevation level refers to height above mean sea level.

R. K. Singh, Union Minister for Power and New & Renewable Energy, reviewed the project’s progress and it was informed then that the project had made significant progress in dam concreting, with 14 blocks having reached a top level of 210 metres and the remaining two blocks scheduled to be completed soon.

Advertising

EPR Android App Banner

NHPC has reported that more than 90 percent of the project’s overall work has already been accomplished. The dam, power house, and hydromechanical works are all nearing completion. The remaining work of radial gates will be completed after the monsoon season and electricity generation is expected to begin by the end of Financial Year 2023-24.

The Subansiri Lower Hydroelectric Project, when completed, will generate roughly 7,500 million kilowatt-hours of power per year in a 90 percent reliable year.

After getting forest clearance on October 12, 2004, NHPC Limited began building on the Subansiri Lower Hydroelectric Project in January 2005. However, due to agitation and protests by local stakeholders, the project building progress was halted from December 2011 to October 2019. Following National Green Tribunal approval, the project construction commenced on October 15, 2019.

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Nirmal Wires
Nirmal Wires
Android App
Android App

Events

Power Gen
Power Gen
India Energy Storage Week 2025
India Energy Storage Week 2025
GOTS 2025
GOTS 2025
Renewable Energy India (REI)
Renewable Energy India (REI)
BEDIC
BEDIC
MEPIC
MEPIC

Our Sponsors

Geda
Geda
Kimbal
Kimbal
BCH India
BCH India
Kp Group
Kp Group
Voltaredox
Voltaredox
Rayzon Solar Pvt Ltd
Rayzon Solar Pvt Ltd
Om Technical Solutions
Om Technical Solutions
Apar Industries
Apar Industries
Ravin Group
Ravin Group
Meco Instruments Pvt Ltd
Meco Instruments Pvt Ltd
Balaji Switchgears
Balaji Switchgears
Gloster Cables Limited
Gloster Cables Limited
HPL Electric Power
HPL Electric Power
K-Lite Industries
K-Lite Industries
Newtech Switchgear
Newtech Switchgear
Elev8 Lift
Elev8 Lift
flir system
flir system
ET Transformers
ET Transformers
Polycab
Polycab
Aeron Composite Pvt Ltd
Aeron Composite Pvt Ltd
OBO Engineered Cable Trays
OBO Engineered Cable Trays
Siemens Energy
Siemens Energy
Radicon Powerbuild
Radicon Powerbuild
MENNEKES Electric India
MENNEKES Electric India
PRAMA HIKVISION INDIA
PRAMA HIKVISION INDIA
TDK Electronics
TDK Electronics