Home » Case Study » ERS tower installation: Supreme repeats its stellar performance

ERS tower installation: Supreme repeats its stellar performance

November 27, 2017 1:54 pm

ERS tower installation: Supreme repeats its stellar performance
.

After the successful erection of the first ever bypass arrangement line by an Indian manufacturer on a high voltage transmission line in Ghaziabad, Supreme achieved yet another feat in Uttar Pradesh.

Construction of a new 400 kV Transmission Line between Atur and Indira Puram, remained suspended since February and was likely to remain idle for more than three months, due to a line crossing over 132 kV Single Circuit Transmission Line between Loni and Mohan Nagar in Uttar Pradesh which required a shut down for 5 to 7 days for unstringing of existing S/C line, followed by stringing of 400 kV Quad-Line, replacing a 132 kV Angled Tower and re-stringing with ACSR conductor near Raja Nagar Extension of Ghaziabad.

To put things in perspective due to this problem of 400 metres, the entire line of 18 kms could not be completed resulting in a massive investment condemned to an indefinite “work in progress status” without getting capitalised. Due to obstruction from 132 kV 5 MW line, power evacuation of 580 MW was getting indefinitely delayed.

Supreme was given an opportunity by UPPTCL to offer a suitable solution, in view of earlier contract executed for a Bypass arrangement between Vaishali and Sahibabad S/C TL.

Supreme’s engineering team conducted a survey and analysis report to install three ERS Towers considering a river, a national highway and flyover crossings for scheduled bypass of four spans.
The project was executed in four days with only a line shutdown of 4 hours on 5th June 2017. It may also be noted that we achieved yet another challenging feat of taking the bypass line and crossing the highway without necessitating the disruption of highway traffic even for a minute and without any shutdown.

The project encountered heavy rain and hailstorm after the execution but no damage was found.

“No heavy machinery or earthmovers were used for the execution of the above, other than for transportation,” Supreme informs.

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Power Talk
Webinar
Webinar
Android App
Android App
EPR eMagazine May 2024
EPR eMagazine April 2024
EPR eMagazine April 2024

Events

EL Asia
EL Asia
Global Energy Digitalisation Conclave
Global Energy Digitalisation Conclave
India Energy Storage Week
India Energy Storage Week
World battery and energy storage industry expo
World battery and energy storage industry expo
Green Hydrogen Summit
Green Hydrogen Summit
Powergen
Powergen
Windergy
Windergy

Our Sponsors

Rayzon Solar Pvt Ltd
Rayzon Solar Pvt Ltd
CSE Power
CSE Power
Calter
Calter
Lawson Fuses
Lawson Fuses
Kusam Meco
Kusam Meco
Apar Industries
Apar Industries
Easun MR Tap Changers
Easun MR Tap Changers
Maco Corporation India Pvt Ltd
Maco Corporation India Pvt Ltd
Bask Energies
Bask Energies
HPL Electric Power
HPL Electric Power
Mecc-Alte India
Mecc-Alte India
flir system
flir system
Triveni Turbine ltd
Triveni Turbine ltd
Innovatek
Innovatek
Aeron Composite Pvt Ltd
Aeron Composite Pvt Ltd
Powerica LTD
Powerica LTD
Electrotherm
Electrotherm
MENNEKES Electric India
MENNEKES Electric India
Om Technical Solutions
Om Technical Solutions
PRAMA HIKVISION INDIA
PRAMA HIKVISION INDIA